  A
 AB  Allocated Baseline  
 AC  Actual Cost AC=ACWP
 ACWP  Actual Cost of Work Performed  
 AD  Activity Description 活動說明書
 ADD  Architectural Design Document  
 ADM  Arrow Diagramming Method 箭頭圖示法
 AF  Actual Finish Date 實際完成日
 AI  Action Item  
 ANSI  American National Standards Institute  
 AOA  Activity-On-Arrow 箭頭圖示活動法
 AON  Activity-On-Node 節點圖示活動法
 ARC  Appraisal Requirements for CMMI  
 ARO  After Receipt of Order  
 AS  Actual Start Date 實際開始日
 ASR  Alternative System Review  
 ATD  Acceptance Test Description  
 ATP  Acceptance Test Plan  
 ATR  Acceptance Test Report  
  B
 BAC  Budget at Completion  
 BCWP  Budgeted Cost of Work Performed BCWP=EV
 BCWS  Budgeted Cost of Work Scheduled BCWS =PV
 BOM  Bill of Material  
  C
 CA  Configuration Audits  
 CAP  Control Account Plan(Cost Account Plan) 控制會計計劃書
 CAR  Causal Analysis and Resolution 原因分析與解決方案
 CBA  IPI CMM-Based Appraisal for Internal Process Improvement  
 CCB  Configuration Control Board  
 CCR  Change Commitment Record  
 CDM  Configuration and Data Management  
 CDR  Critical Design Review 關鍵設計評審
 CD&UT  Coding and Unit Testing phase 編碼與單元測試階段
 CI  Configuration Item  
 CL  Capability Level 能力等級
 CM  Configuration Management 建構管理/配置管理/型態管理
 CMB  Change Management Board  
 CMM  Capability Maturity Model 成熟度模型
 CMMI  Capability Maturity Model Integration  
 CMU  Carnegie Mellon University  
 CPC  Computer Programming Manual  
 CPFF  Cost Plus Fixed Fee Contract 成本加固定報酬合約
 CPI  Cost Performance Index CPI = BCWP/ACWP 成本績效指數
CPI= EV/AC
 CPIF  Cost Plus Incentive Fee Contract 成本加獎金合約
 CPM  Critical Path Method 要徑法
 CPU  Central Processing Unit  
 CRISD  Computer Resources Integrated Support Document  
 CRLCMP  Computer Resource Life Cycle Management Plan 電腦資源生命週期管理計畫
 COSM  Computer System Operator's Manual  
 CS  Critical Software  
 CSC  Computer Software Component  
 CSCI  Computer Software Configuration Item  
 CSD  Collaborative Software Development  
 CSU  Computer Software Unit  
 CV  Cost Variance CV= BCWP-ACWP 成本變異
 CVS  Concurrent Versions System  
 CWBS  Contract Work Breakdown Structure  
 CWS  Collaborative Workspace  
  D
 DAR  Decision Analysis and Resolution 決策分析與解決方案
 DB  Development Baseline  
 DBDD  Database Design Description 資料庫設計描述
 DCO  Document Change Order  
 DCR  Document Change Request  
 DD  Detailed Design phase 詳細設計階段
 DD  Data Date 資料日
 DDD  Detailed Design Document 詳細設計文檔
 DDR  Detailed Design Review  
 DID  Data Item Description 資料項目描述
 DL  Design Level  
 DoD  Department of Defense  
 DR  Discrepancy Report  
 DRN  Document Revision Notice  
 DTD  Document Type Definition 期程
 DU  Duration  
  E
 EAC  Estimate at Completion  
 ECN  Engineering Change Notice  
 ECO  Engineering Change Order  
 ECP  Engineering Change Proposal  
 ECR  Engineering Change Request  
 EF  Early Finish Date 早完成日
 EIA/IS  Electronic Industries Alliance/Interim Standard  
 EO  Engineering Order  
 ERB  Engineering Review Board  
 ES  Early Start Date 早開始日
 ETC  Estimated to Completion 完工之剩餘成本評估
 EV  Earned Value EV= BCWP
 EVM  Estimated Value Management  
  F
 FA  Functional Audit 功能檢查
 FCA  Functional Configuration Audit 功能配置審查
 FF  Free Float 自由浮時
 FF  Finish-to-Finish 結束到結束
 FFP  Firm Fixed Price 絕對固定價格
 FI  Formal Inspection 正式檢查
 FP  Function Point  
 FPIF  Fixed Price Incentive Fee 固定價格加獎金
 FQR  Formal Qualification Review  
 FQTD  Formal Qualification Test Description  
 FQTP  Formal Qualification Test Plan  
 FQTR  Formal Qualification Test Report  
 FS  Finish-to-Start 結束到開始
 FSM  Firmware Support Manual  
 FVT  Functional Verification Test  
  G
 GEIA  Government Electronics and Information Technology Association  
 GERT  Graphical Evaluation and Review Technique 圖解評核術
 GG  Generic Goal  
 GP  Generic Practice  
   H
 HB  HandBook  
 HDDs  Hardware Design Descriptions /Drawings  
 HRSs  Hardware Requirement Specifications  
 HWCI  Hardware Configuration Item  
  I
 IDD  Interface Design Description 介面設計描述
 IDS  Interface Design Specification  
 IEEE  The Institute of Electrical and Electronics Engineers, Inc.  
 IFB  Invitation for Bid 投標邀請函
 IMP  Integrated Master Plan  
 IMS  Integrated Master Schedule  
 IPD-CMM  Integrated Product Development Capability Maturity Model  
 IPM  Integrated Project Management 整合的專案管理
 IPPD  Integrated Product and Process Development  
 IPT  Integrated Product Team  
 IS&AC  Installation and Acceptance phase 安裝與驗收階段
 ISO  International Organization for Standard  
 ISR  Interim System Review  
 IT  Integrated Teaming 整合團隊活動
 ITP  Integration Test Plan  
 IT&ST  Integrating and System Testing phase 組裝與系統測試階段
 IVP  Integration and Verification Plan  
 IVR  Integration and Verification Report  
 IV&V  Independent Verification and Validation 獨立驗證與確認
 IWS  Individual Workspace  
  K
 KLOC  thousands of lines of code  
 KOM  Kick-off Meeting  
 KPA  Key Process Area 關鍵流程域
 KSLOC  thousands of source lines of code  
  L
 LF  Late Finish Date 晚完成日
 LOC  lines of code  
 LS  Late Start Date  
  M
 MA  Measurement and Analysis 度量與分析
 MPM  Modern Project Management 現代專案管理
 MRR  Material Review Report  
 MTBF  Mean Time Between Failure  
 MTTF  Mean Time to Failure  
 MTTR  Mean Time to Repair  
  N
 NDS  Non-Developmental Software 不可開發軟體
 NOR  Notice of Revision  
  O
 OBS  Organization Breakdown Structure  
 OCD  Operational Concept Description  
 OEI  Organization Environment for Integration 適於整合的組織環境
 OID  Organizational Innovation and Deployment 組織創新與推展
 OO  Object-Oriented  
 OPD  Organizational Process Definition 組織流程定義
 OPF  Organizational Process Focus 組織流程專注
 OPP  Organizational Process Performance 組織流程績效
 OT  Organizational Training  
 OT&E  Operational Test and Evaluation  
  P
 PA  Physical Audit  
 PB  Product Baseline  
 PC  Percent Complete 完成百分比
 PCA  Physical Configuration Audit  
 PCO  Procedure Change Order  
 PD  Preliminary Design Phase  
 PDD  Preliminary Design Document  
 PDL  Program Design Language  
 PDM  Precedence Diagramming Method 優先順序圖示法
 PDR  Preliminary Design Review 初步設計評審
 PERT  Program Evaluation and Review Technique 計畫評核法
 PF  Planned Finish Date 計畫完成日
 PI  Product Integration 產品整合
 PIP  Project Implementation Plan  
 PLCS  Product Life Cycle Support  
 PLM  Product Lifecycle Management  
 PM  Project Management /Project Manager  
 PMBOK  Project Management Body of Knowledge  
 PMC  Project Monitoring and Control 專案監控
 PMI  Project Management Institute  
 PMP  Project Management Professional 專案管理師(證照)
 PP  Project Planning 專案規劃
 PPB  Preliminary Product Baseline PPB= Development Baseline (DB)  
 PP&O  Project Planning and Oversight 專案計畫與監督
 PPQA  Process and Product Quality Assurance 流程與產品品質保證
 PR  Problem Report  
 PRR  Product Readiness Review 產品準備就緒評審
 PS  Planned Start Date 計劃開始日
 PSP  Personal Software Process  
 PV  Planned Value PV=BCWS
 PVT  Product Verification Test  
 PWBS  Program Work Breakdown Structure  
  Q
 QA  Quality Assurance 品質保證
 QC  Quality Control 品質控制
 QPM  Quantitative Project Management 量化專案管理
  R
 RA  Requirements Analysis phase 需求分析階段
 RAD  Rapid Application Development  
 RAM  Responsibility Assignment Matrix 工作指派(及責任)矩陣
 RD  Requirements Development  
 RDU  Remaining Duration 剩餘期程
 REQM  Requirement Management 需求管理
 RFD/RFW  Request for Deviation/Waiver  
 RFP  Request for Proposal 邀標書(可協商)
 RFQ  Request for Quotation 邀標書(不可協商)
 RM  Review Meeting  
 ROI  Return of Investment  
 RPL  Review Problem 評審中發現的問題的記錄
 RSKM  Risk Management 風險管理
 RSR  Review Summary Report 評審總結報告
 RUP  Rational Unified Process  
  S
 SADT  Structured Analysis and Design Technique  
 SAM  Supplier Agreement Management 供應商協議管理
 SA&SD  System Analysis and Software Definition phase 系統分析與軟體定義階段
 SCAMPI  Standard Appraisal Method for Process Improvement
()
 
 SCE  Software Capability Valuation  
 SCL  Source Code Library  
 SCM  Software Configuration Management 軟體配置(建構/型態)管理
 SCMP  Software Configuration Management Plan 軟體配置(建構/型態)管理計畫
 SCN  Specification Change Notice  
 SCO  Software Change Order  
 SD  System Design  
 SDCE  Software Development Capability Evaluation  
 SDD  Software Design Document, Software Design Description 軟體設計文檔(分成概要設計說明書[PDD]和詳細設計說明書[DDD])
 SDDD  System/Segment Design Document  
 SDF  Software Development File 軟體開發文件
 SDL  Software Development Library 軟體開發庫
 SDP  Software Development Plan 軟體開發計畫
 SDR  System Design Review 系統設計審查
 SEDS  System Engineering Detailed Schedule  
 SEI  Software Engineering Institute 軟體工程學會
 SEMS  Systems Engineering Master Schedule  
 SEPG  Software Engineering Process Group  
 SEPO  Software Engineering Process Office 軟體工程流程辦公室
 SF  Scheduled Finish Date 預定完成日
 SF  Start-to-Finish 開始到結束
 SFR  System Functional Review  
 SG  Specific Goal  
 SIOM  Software Input/Output Manual  
 SIP  Software Installation Plan  
 SIT  System Integration Test  
 SLOC  source lines of code  
 SOW     Statement of Work 工作說明
 SP   Specific Practice  
 SPI  Software Process Improvement  
 SPI  Schedule Performance Index SPI=BCWP/BCWS 時程績效指數SPI=EV/PV
 SPIN  Software Process Improvement Network  
 SPM  Software Program's Manual  
 SPMP  Software Project Management Plan 軟體問題報告單
 SPR  Software Problem Report  
 SPS  Software Product Specification 軟體品質保證
 SQA  Software Quality Assurance  
 SQAP  Software Quality Assurance Plan 軟體品質保證計畫
 SRD  Software Requirement Document  
 SRR  Software/System Requirement Review 軟體/系統需求審查
 SRS  Software Requirement Specification 軟體需求規格說明
 SRSs  Software Requirement Specifications  
 SS  Start-to-Start 開始到開始
 SSDD  System/Subsystem Design Description 系統/子系統設計描述
 SSR  Software Specification Review 軟體規格說明審查
 SSS  System/Subsystem Specification 系統/子系統規格說明
 ST  System Test  
 STD  Software Transfer Document / Software Test Description  
 STP  System/Software Test Plan  
 STR  System/Software Test Report, Software Trouble Report  
 STrP  Software Transition Plan  
 STSC  Software Technology Support Center 軟體技術支援中心
 SUM  Software User Manual 用戶手冊
 SV  Schedule Variance  
 SVD  Software Version Description 軟體版本描述
 SVR  System Verification Review  
 SVT  System Verification Test  
 SVVP  Software Verification and Validation Plan 軟體驗證與確認計畫
 SVVPR  Software Verification and Validation Plan Review  
 SVVR  Software Verification and Validation Review 軟體驗證與確認評審
 SW 或  S/W  Software  
 SWAP  Software Action Plan  
 SW-CMM  Capability Maturity Model for Software 軟體成熟度模型
  T
 TC  Target Completion Date 目標完工日
 TCR  Test Completion Review  
 TDR  Test Discrepancy Report  
 TF  Total Float 總浮時
 TF  Target Finish Date   目標完成日
 TQM  Total Quality Management 全面品質管理
 TR  Technical Report  
 TS  Target Start Date 目標開始日
 TS  Technical Solution 技術解決方案
 TSP  Team Software Process  
 TSSD  Total Software System Development phase 整個軟體系統的開發階段
  U
 UAT  User Acceptance Test 驗收測試
 UDF  Unit Development Folder 單元開發檔案夾
 UML  Unified Modeling Language  
 URD  User Requirement Document  
 UTP  Unit Test Plan  
  V
 VAC  Variance at Completion VAC=BAC-EAC  
 VAL  Validation 確認
 VDD  Version Description Document  
 VE  Value Engineering 價值工程
 VER  Verification 驗證
 V&V  Validation and Verification  
  W
 WBS  Work Breakdown Structure 工作明細結構
  X
 XP  eXtreme Programming  

 